Grid Congestion and Operational Challenges in India’s Renewable Energy Expansion
Background
India is rapidly expanding its renewable energy capacity as part of its broader energy transition and climate commitments. The country has set ambitious targets for solar and wind energy deployment, and large investments are flowing into renewable projects across multiple states.
This rapid growth has positioned India as an important global player in clean energy development. However, the expansion of generation capacity has also exposed operational challenges in the power transmission and grid management system.
One of the most prominent examples is Rajasthan, a state with some of the highest renewable energy potential in the country. Despite large installed capacity, a significant portion of renewable electricity cannot be transmitted to the grid during peak hours due to transmission congestion.
Renewable Energy Capacity in Rajasthan
Rajasthan has developed a large renewable energy base over the past decade.
Key figures include:
- Around 23 gigawatts (GW) of installed renewable capacity in the state
- Transmission infrastructure capable of evacuating approximately 18.9 GW
This difference between generation capacity and transmission capability creates a gap that leads to power curtailment.
If this gap were managed proportionately, about 15 percent of renewable power would need to be curtailed during peak hours. While inconvenient, such a level of curtailment could still be manageable for project developers.
However, the actual operational practice has created uneven consequences for certain projects.
Curtailment and the Role of Network Access
Renewable energy projects in India operate under different types of grid access permissions, known as General Network Access (GNA).
There are two main types:
- Permanent General Network Access (GNA)
- Temporary General Network Access (T-GNA)
Under current operating practices in Rajasthan:
- Projects with Permanent GNA continue to operate normally
- Projects with Temporary GNA are often completely shut down during peak solar hours
Instead of distributing curtailment evenly, the system places the entire burden on T-GNA projects, leading to 100 percent shutdowns for some generators during certain periods.
Many of these projects were developed after fulfilling all regulatory requirements and completing construction within approved timelines. As a result, the shutdowns create financial stress for developers who had planned operations based on approved connectivity arrangements.
Underutilisation of Transmission Infrastructure
Another concern is the underutilisation of high-capacity transmission corridors.
India has built large transmission lines designed to carry electricity from renewable-rich regions to demand centres.
For example:
- 765 kilovolt (kV) double-circuit transmission corridors
- Each corridor designed to evacuate around 6,000 megawatts (MW)
- Construction cost of approximately ₹4,000–₹5,000 crore
However, many of these lines are currently operating at only 600–1,000 MW, which represents less than 20 percent of their design capacity.
This means that:
- Transmission infrastructure remains significantly underused
- Renewable plants remain connected but unable to supply electricity
The result is a mismatch between installed infrastructure and actual system utilisation.
Institutional Responsibility and Mandate
The situation raises an important institutional question regarding the role of Grid India, the national grid operator.
Traditionally, the primary responsibility of grid operators has been to maintain grid stability and prevent system failures. Stability is essential because power system disturbances can lead to large-scale blackouts.
However, when grid operators focus exclusively on stability without considering efficient utilisation of infrastructure, the system may become overly conservative.
Transmission infrastructure in India involves public investment exceeding ₹1 lakh crore, and its cost is ultimately recovered through electricity tariffs paid by consumers.
When such infrastructure operates far below capacity:
- Consumers pay for assets that deliver limited value
- Renewable energy generation remains stranded
This creates inefficiencies across the entire electricity system.
Asymmetry in Risk Distribution
The current operational framework distributes risks unevenly among stakeholders.
Transmission infrastructure that remains underutilised does not trigger strong institutional consequences. There are:
- No clear utilisation benchmarks
- No automatic performance reviews
- Limited public transparency when infrastructure performs below expectations
In contrast, renewable energy generators face direct financial losses due to curtailment.
This creates a situation where system inefficiencies are absorbed primarily by power producers rather than system operators.
Technical Causes of Grid Constraints
The operational limits in Rajasthan are largely attributed to technical issues related to grid stability.
Some of the commonly cited challenges include:
- Voltage oscillations
- Risk of grid instability during peak solar generation
These challenges are real and must be managed carefully. However, modern power systems around the world address similar problems using advanced grid management technologies.
Examples include:
- STATCOMs (Static Synchronous Compensators)
- Advanced reactive power management devices
- Special protection schemes for grid stability
Many renewable plants in India are already equipped with equipment such as:
- Static VAR generators
- Harmonic filters
Despite this, operational restrictions still prevent many projects from injecting electricity into the grid.
This suggests that the main issue may not always be technological limitations but rather slow deployment of available solutions and cautious operational policies.
Operational Conservatism in Grid Management
Grid security is an essential priority in power system management. However, when stability becomes the only performance indicator, operators may adopt extremely cautious practices.
Operating a high-capacity transmission corridor at 15–20 percent utilisation may minimise short-term risks, but it also leads to:
- Underutilisation of infrastructure
- Curtailment of renewable generation
- Higher overall system costs
In many advanced electricity systems, grid operators use modern operational approaches that balance security with efficient utilisation.
These approaches include:
- Dynamic security assessment
- Real-time contingency analysis
- Probabilistic risk evaluation
- Adaptive transmission line ratings
Such tools allow grids to carry more power while maintaining reliability.
Disconnect Between Planning and Operations
Another structural issue arises from the gap between transmission planning and operational implementation.
The Central Transmission Utility (CTU) plans transmission corridors based on projected renewable capacity and allocates General Network Access to developers accordingly.
Developers then invest in projects based on the expectation that:
- Transmission infrastructure will be built
- Adequate evacuation capacity will be available
However, in some cases the operational capacity permitted by the grid operator is far below the planned design capacity.
For example:
- Transmission lines designed for 6,000 MW
- Operationally limited to 1,000 MW
This discrepancy creates uncertainty for developers who have invested large sums of capital based on planning approvals.
Policy Recommendations
Addressing these challenges requires improvements in institutional frameworks rather than compromising grid security.
Several reforms could help improve the functioning of the system.
Clear Operational Mandate
Grid India should be responsible not only for maintaining system stability but also for maximising the utilisation of transmission assets within safe operating limits.
Performance evaluation of grid operators should include both reliability and efficiency indicators.
Fair Distribution of Curtailment
In regions facing transmission constraints, curtailment should be shared proportionately across all generators, rather than imposed entirely on projects with temporary network access.
This would distribute the burden of congestion more equitably.
Dynamic Reallocation of Network Access
Unused or underutilised General Network Access capacity should be reallocated dynamically through transparent and real-time mechanisms. This would allow available transmission headroom to be used more efficiently.
Institutional Review Mechanisms
Whenever large transmission assets consistently operate below their expected capacity, automatic review processes should be triggered.
These reviews should identify whether the constraints arise from:
- Technical issues
- Operational policies
- Delays in system upgrades
The findings should be made public to improve transparency and accountability.
Conclusion
India’s renewable energy transition has achieved remarkable progress in terms of capacity expansion and investment flows. However, the effectiveness of this transition depends not only on building new infrastructure but also on ensuring that existing infrastructure operates efficiently.
The case of Rajasthan demonstrates how grid congestion, operational conservatism, and institutional gaps can lead to stranded renewable capacity despite significant investment.
For India’s clean energy transition to succeed, the electricity system must balance grid stability with efficient utilisation of assets, ensure fair treatment of market participants, and maintain transparency in operational decision-making. Only then can the power system fully support the country’s long-term renewable energy ambitions.
